MCN delivered the full electrical installation for a commercial unit in Leeds, including the design and build of a new high-specification distribution board, power and lighting circuits, containment infrastructure and final connections. The specification called for premium Schneider Electric Acti9 protective devices throughout, providing best-in-class protection across all final circuits.
Scope of Works
Design and installation of new multi-way commercial distribution board in recessed blockwork enclosure
Galvanised steel trunking and cable containment infrastructure throughout the unit
Installation of Schneider Electric Acti9 iCV40H VigiARC arc fault detection RCBOs (AFDD) on all final circuits
Schneider iCT 40A contactors for time-controlled lighting and plant switching circuits
Surge protection device (SPD) installation at the DB incoming supply
Power and lighting circuit installation, socket outlets and final connections
Full testing and certification to BS 7671:2018 + A2:2022
Equipment & Specification
The distribution board was built to a high specification using Schneider Electric Acti9 devices throughout. VigiARC arc fault detection technology was specified on all final circuits, offering a significant uplift in fire safety protection over standard RCBO devices. A class II SPD was installed at the origin to protect against transient overvoltages.
Delivery
The installation was completed within a tight programme to support the client’s fitout schedule, with all circuits tested, certified and handed over on time.