Comparing plumbing and heating package quotes: scope gaps to check

How to compare plumbing, heating and gas package quotes on new-build developments: check inclusions, exclusions, free-issue items, testing, notifications and programme.

MCN Mechanical & Electrical · · 4 min read

When plumbing, heating and gas package quotes come back for a new-build development, the lowest total is only useful if every tenderer has priced the same work. Before comparing figures, line up each quote against one scope list: what is supplied, what is installed, what is tested and notified, what is assumed about the programme, and what is excluded. Differences in those boundaries can materially affect the apparent price.

This article is for housebuilders, developers, main contractors, quantity surveyors and project managers who have already issued an enquiry. If you are still preparing one, start with our guide to new-build plumbing tenders.

Build one comparison sheet before reading the totals

Put every quote on a single sheet, with a row for each scope item and a column for each tenderer. Mark each row as included, excluded, provisional or not mentioned. An item marked "not mentioned" leaves an unresolved scope question, so ask the tenderer to confirm it in writing rather than assuming either way.

Check that every quote is based on the same drawing revision, plot schedule and house-type mix. A quote priced on an earlier revision may look cheaper simply because it covers less pipework or fewer plots.

Supply: who provides the equipment?

Free-issue items move cost from the package to the client's own budget, so a quote that excludes them is not comparable with one that includes them. For each house type, confirm who supplies:

boilers, heat pumps or other heat sources, and their flues;

hot-water cylinders and their safety components;

radiators, underfloor heating manifolds and controls;

sanitaryware, taps and showers;

pipe, fittings and consumables.

Where an item is free-issue, check who orders it, who receives and stores it on site, and who is responsible for damage or loss before it is fixed.

Installation boundaries with other trades

Package quotes often stop at a point another trade is expected to start. Common boundaries to confirm are builder's work in connection, such as forming holes, sleeving and fire-stopping; above-ground soil and waste; condensate and discharge pipework; and connections to the incoming water and gas supplies. Our article on plumbing and heating programme coordination explains how those hand-offs affect the programme.

Ask each tenderer where its gas work starts and finishes, and who provides the meter. The meter is usually arranged through the gas supplier and transporter, not the plumbing package, as described in our guide to gas supply and meters on new-build plots.

Testing, commissioning and notifications

Testing and paperwork take time on every plot, so check that each quote includes them rather than treating them as extras. Compare who carries out pressure and gastightness tests, flushing and system cleaning, commissioning of heat sources and controls, and completion of commissioning checklists. Our guide to first and second fix plumbing sign-off sets out what each stage normally covers.

Ask the contractor and project team to identify the water-undertaker notifications, building-control notices and commissioning records required for the project. Agree who submits each item, when it is needed and whether the cost is included. Requirements depend on the work and jurisdiction, so confirm the applicable process before installation starts.

Ask each tenderer for current Gas Safe registration details and check that the business and proposed engineers are qualified for the specific gas work. Record who will supply the installation and commissioning documentation at handover.

Programme and commercial assumptions

Two quotes for the same scope can still differ because they assume different working conditions. Compare:

the number of plots released at a time and the visits allowed per plot;

whether return visits for other trades' delays are included;

temporary water or heating, if needed before permanent supplies are live;

attendances, such as welfare, storage, waste removal and access equipment;

snagging visits and who responds during the defects period;

the validity period of the quote and how price changes are handled.

Any provisional sum should state what it covers. If a heat source or specification has not been fixed, ask every tenderer to price the same assumption so that the comparison stays fair.

Close the gaps before appointment

Once the comparison sheet shows the gaps, send the same clarification questions to every tenderer and ask for responses in writing. Record the agreed scope, exclusions and assumptions in the subcontract so that the site team, QS and package contractor work from the same list.

If you would like MCN Mechanical & Electrical to price your next development, send us your drawings, plot schedule and programme and tell us which items are free-issue. You can find out more about our new-build plumbing, heating and gas packages.

Further guidance: The Water Supply (Water Fittings) Regulations 1999, regulation 5 (notification, England and Wales) · The Building Regulations 2010, regulation 44 (commissioning, England and Wales versions) · The Gas Safety (Installation and Use) Regulations 1998, regulation 4 (duty on employer)