A plumbing, heating and gas package rarely fails on duration alone. It slips when it has to wait for another trade, or when another trade closes up work that has not yet been tested. The most reliable way to coordinate the package is to programme it as a series of hand-offs: what must be finished by others before the package starts a stage, and what the package must hand on, tested and recorded, before the next trade follows. Agree those conditions before appointment and put them in the tender.
This article is for housebuilders, developers, main contractors, QSs and project managers. It complements our guides to new-build plumbing tenders and first and second fix plumbing sign-off.
Programme the hand-offs, not just the durations
A bar chart that shows "first fix, 5 days" says little about what must be true on day one. For each plot or plot type, list the hand-offs in both directions:
Into the package: structural openings and sleeves, partitions set out, floor and roof framing agreed for pipe routes, flue and ventilation positions fixed, drawing revisions confirmed, and access and storage available.
Out of the package: first-fix pipework tested and released before boarding and screeding, heating pipework tested before it is covered, and records filed against the plot.
Each hand-off needs a named person who confirms it, so that the next trade is not left to guess whether a plot is ready.
Coordinate penetrations with the trades that form and seal them
Plumbing and heating pipework passes through floors, walls and fire-separating elements. MCN Mechanical & Electrical does not form, sleeve or fire-stop those openings; other trades do. The package must give those trades pipe positions, sizes and materials on the same drawing revision as the builder's work drawings. The programme should then show when each opening is formed, when the pipework is installed through it, and when it is sealed and inspected before it is hidden.
The guidance on pipe penetrations differs across Great Britain, so confirm which applies to each site:
England: Approved Document B, Volume 1 (Dwellings), section 9, says pipe openings should be as few as possible, as small as practicable and fire-stopped, allowing for thermal movement. Pipes through a fire-separating element need a proprietary tested seal, fire-stopping within the Table 9.1 diameter limits, or a sleeve where permitted.
Wales: the Welsh Government's Approved Document B, Volume 1 (Dwellinghouses), section 8, sets out the same three alternatives for pipes (paragraphs 8.6 to 8.9) and the same few, small and fire-stopped rule (paragraph 8.12). Flats are covered by Volume 2.
Scotland: the Domestic Technical Handbook, section 2 (Fire), clause 2.2.9, says a service opening through a separating wall or floor should be fire stopped to at least the wall or floor's fire resistance duration. It lists limited exemptions by pipe size, spacing and material.
Ask the designer to state the option on the drawings, so the fire-stopping trade can price and programme the right product.
Protect tested work between first and second fix
Between the two fixes, plasterboard, floor decks and screeds will bury pipework unless it has already been tested and released. The Contract Flooring Association (CFA) guidance on underfloor heating, compiled with BEAMA, says the system should be run through a full heat-up and cool-down cycle before any floor covering is laid. It says this commissioning period is usually around 21 days, and that moisture tests follow. Ask the designer and screed supplier to confirm the detail for each plot.
MCN Mechanical & Electrical installs and commissions underfloor heating on new-build developments, and the commissioning cycle still depends on other trades. A heat source, power and water must be available when the screed is ready to commission, and floor finishes cannot start until the cycle has finished. If the permanent boiler cannot be commissioned because gas or the meter is not ready, decide early whether temporary heat will be used and who provides it. Our article on gas supply and meters on new-build plots covers the meter, addressing and gas-on sequence.
Plan second fix around the trades that follow
Second fix depends on several trades finishing their own work. Electricians must complete supplies and controls wiring before heating controls can be commissioned. Kitchen and bathroom fitters need set-out information and tested supplies. Agree which valves and access points stay accessible after finishes, and walk a sample plot with the main contractor's site manager before the plot sequence is repeated across the development.
Decide who coordinates and how
Under the Construction (Design and Management) Regulations 2015, which apply across Great Britain, the principal contractor must plan, manage, monitor and coordinate the construction phase, which includes organising cooperation between contractors. The package contractor should give the principal contractor a sequence that fits that plan. MCN Mechanical & Electrical provides look-ahead programmes and agrees notice periods with the main contractor, so that conflicts surface at coordination meetings before they cost time on site.
For apartment blocks, add the communal plant room and risers to the same hand-off list. Our guide to plant room planning for apartment blocks explains what to agree early.
Put the programme assumptions in the tender
Each tenderer should price the same programme. Include with the enquiry:
The master programme and the plot-release sequence, with the last-revised date.
The plot types, with floor construction and whether underfloor heating is specified.
Who provides temporary power, water, heat, access and storage.
Which trades form openings, sleeve them and fire-stop penetrations, and when.
The hand-off conditions for first fix, second fix and commissioning.
The notice period you expect to give before each release.
Ask tenderers to list the assumptions they have priced, so quotations compare like for like.
Planning the sequence for a residential development? Send MCN Mechanical & Electrical your master programme, plot-release schedule, house types and heating specification. Read about our new-build plumbing, heating and gas packages or send us an enquiry.
Further guidance: HSE, Principal contractors: roles and responsibilities (CDM 2015) · The Construction (Design and Management) Regulations 2015, regulation 13 (duties of a principal contractor) · GOV.UK, Fire safety: Approved Document B (England; Volume 1: Dwellings, section 9, openings for pipes and fire-stopping, paras 9.2-9.5 and 9.24) · GOV.WALES, Approved Document B: fire safety (Wales; landing page with current volumes and amendment slips) · Welsh Government, Approved Document B Volume 1: Dwellinghouses, 2006 edition incorporating 2010, 2016 and 2020 amendments (section 8, paras 8.6-8.9 and 8.12) · Scottish Government, Building Standards Technical Handbook - Domestic, April 2026 edition (section 2 Fire, clause 2.2.9 openings and service penetrations) · Contract Flooring Association (CFA) / BEAMA, Beyond Installation: Guidance on Underfloor Heating (section 10, screed start up / drying out)