All Case Studies
Gateshead · Mechanical

Mechanical Services Refurbishment
Civic Office Building, Gateshead

We delivered the full mechanical services package for the refurbishment of a 1960s municipal office building within the Gateshead Civic Centre estate - working around a live building to deliver a complete heating and welfare upgrade on programme.

Scope of Works

  • Full strip-out of existing heating systems
  • Installation of new LTHW heating system with zoned distribution
  • Replacement of heating pipework using threaded steel pipework (exposed runs)
  • Installation of new panel radiators throughout
  • Upgrades to welfare areas including sanitaryware and point-of-use water heaters
  • Installation of mechanical extract ventilation to toilets and internal spaces
Location Gateshead Civic Centre, Gateshead
Sector Public Sector / Commercial
Services Mechanical - Heating, Plumbing & Ventilation
Duration ~24 weeks
Discuss a Similar Project